As early as 1913, the concept of a 2. Defense line and the associated field fortifications at strategically important points in the south and east of Tyrol again in the focus of the national defense and the genius directorates Brixen, Trento and Riva. In the Brixen area these were the well-known areas between Valser Joch and the plateau of Natz-Schabs, around Franzensfeste, from Scheibenberg to Ochsenhügel and in the south the barrier Klausen-Villnöss.
1914
One of the first documents documenting a resumption of planning is the map below, which shows the Verdings – Theis positions.
The military map dated 28 March 1914 shows the planned and, as we shall see later, also largely erected field positions between Verdings and Teis. However, for strategic reasons, partial shifts were made to the course of the plant.
The following documents come from reports on the state of work of the field fortification works or the work reports of the Brixen Geniedirektion to the k.u.k. Military Command Innsbruck. Some of the reports also went directly to the coordinator of the South-West defence, General of the cavalry Franz Rohr, between 28 August 1914 and 23 May 1915.
Title page of the first report document, in which the lock Klausen during the 1. World War I is mentioned. It is signed by Lieutenant Colonel Lempruch and countersigned by Major General Friedl of the k.u.k.
25 August 1914
Under point 5, paragraph a) Klausen you can read the following:
Voluntary workers, tools and material ensured for tomorrow, 26th, afternoon, line train indicated by Geniedirektion (Brixen, N.d.V.), construction of the plant begins tomorrow afternoon (continued. Workman's assistant Schmidt and 1 fort. master craftsman).
Colonel von Schliessler is likely to have a personal influence on the building tomorrow afternoon. More details in the next report.
28 August 1914
The reference expressly made in the report of 28 August 1914 to the fact that ‘many voluntary workers from the intelligentsia participated in the construction of these fortifications’ is worth mentioning in addition.
1 September 1914
The genetic sketch of the Brixen Genius Directorate shows not only all the names of the reconnoiters, project designers, site managers and their plans, but also the start and end of construction.
Fortress artillery plant assistant Schmidt had recognosted and projected, from 29 November 1914 Sappeur-Captain Brandmayer.
The overhead line was transferred to Lieutenant Colonel von Lempruch.
From November 26, 1914 to January 30, 1915, fortress artillery works assistant Schmidt had also over the construction management, from January 31, 1915 until the closure of construction Oberleutnant Ettmayr.
The first phase of construction began on 26 August 1914 and ended on 8 September 1914.
The second construction phase began on 8 September of the same year.
Legend: red = partially covered infantry positions, blue = field-related wire or barbed wire obstructions
On the above partial view of the map Klausen and surroundings 1:75,000, the first field-based defenses can be seen. For their defense, a crew of a battalion with two mobile field guns was intended.
The two infantry positions between Latzfons and Yarn were not carried out, because they should be removed if necessary by the crew themselves. It was also proposed to use the artillery mobile, for example on the existing gufid soup.
That not all were of the same opinion can be seen from the document written and signed by Lieutenant Colonel Lempruch on 1 September 1914, together with an enclosed sketch. According to his opinion, 13⁄4 company and 1 company had to be provided as a reserve in Feldthurns for the occupation of the positions on the right bank of the Isarco (Klamm-Verdings). For the occupation of the left bank of the Isarco, provide 1 company for positions near Gufidaun and for the small bases upstream of the town of Gufidaun up to the height of ‘Zicker’ 1 1⁄4 company. Last but not least, he suggested that a ferry be built above the bridge to Villnöss, which could serve as a connection between the two banks if the bridge were destroyed. There was enough material nearby anyway.
In order to support his opinion visually, he also provided his report with a sketch on a scale of 1:25,000.
In the following sketch of the right bank of the Isarco, the positions behind yarn to be carried out only in the event of an emergency are visible under Nos XV and XVI.
legend right wing (Feldthurn side) of the Klausen-Villnöss barrier
| I | Base with extensive infantry cover for 11⁄2 platoon and dummy buildings |
| Ia | Base with partly covered, partly uncovered infantry covers for 1 platoon |
| II | Base with partly covered, partly uncovered infantry covers for 2 trains with Apparent buildings |
| III | Base with partly covered, partly uncovered infantry covers for 1⁄2 platoon |
| IV | two bases with partly covered, partly uncovered infantry covers for 1 platoon |
| V | Base with partly covered, partly uncovered infantry cover for 1⁄2 platoon |
| XV & XVI | Infantry covers for 1 to 2 trains to be produced by own crew as required |
Artillery: mobile use, as installation space is available in the terrain
xxxxxxxxxx = field-related wire barriers
A) Possible rafts to be produced, for which wood for the composition of a strong raft there on the left bank, the wire rope at the road railing next to Klausen are available.
Signature: Schmidt Colonel
On the the following A sketch of the left bank of the Isarco appears at the forward bases VIII to XIV “Zicker” with the positions of plasters up to the bank of the Isarco already secured with barbed wire. However, a position in the village of Gufidaun, near Schloss Sommersberg, and the position in the Villnösserbach seem either not yet built or unsecured. There is no trace of the later variant Nafen-Theis.
legend left wing (Gufidaun side)
| VI & VII | two groups of small bases partly open, partly covered infantry cover for 11⁄2 platoon |
| VIII & XIV | small half-covered bases for 1⁄4 train each |
Artillery: mobile use, as installation space is available in the terrain
xxxxxxxxxx = field-related wire barriers
A) Possible rafts to be produced, for which wood for the composition of a strong raft there on the left bank, the wire rope at the road railing next to Klausen are available.
Signature: Schmidt Colonel
1 September 1914
In the report on the state of the fortification work of September 1, 1914, the author still seems somewhat ignorant about this part of the Isarco Valley, for he confuses the Isarco with the Rienzufer.
5 September 1914
The report of September 5, 1914, already announced a large-scale completion of the defenses, but on closer inspection it is noticed that neither the proposed extension to Yarn nor the outposts at Gufidaun considered essential were finished. However, according to the reports of 12, 19 and 27 September 1914, the work seems to have already been completed.
12 September 1914
19 September 1914
27 September 1914
With regard to accommodation or winter supply for the field-related facilities, the k.u.k. Geniedirektion in Brixen reports to the k.u.k. Befestigungsbaudirektion in Innsbruck on 27 September 1914 on the measures taken that in the Klausen-Villnöss barrier, the numerous residential buildings and heated huts in a favourable location for combat positions make special accommodation provisions seem superfluous.
3 October 1914
As of October 3, 1914, according to reports, all field fortifications in the vicinity of the Isarco Valley appear to have been completed. That this did not correspond to the truth, we will soon see. The k.u.k. Befestigungsbaudirektion in Innsbruck also receives the same notification on 9 October 1914.
A change is imminent
With 17 October 1914, the considerations of the higher commands regarding the Klausen – Villnöß lock seem to have changed somewhat, because they confirm their completion again, but we are now talking about a recognostication for a 2. Line of defense on the left wing. ‘The reconnaissance of the Nafen – Theis line will be carried out in the very next few days, in accordance with the oral instructions given to me by the director of fortifications. Report to follow’.
Lieutenant Colonel Lempruch follows an oral order of 13 October 1914 and, together with Lieutenant Colonel Franz Buchecker, makes a reconnaissance in the Ticino area with the task of determining whether the transfer of the left wing of the Klausen – Villnöß barrier to the Teis – Nafen line could be carried out. The result is recorded in writing in the report of 22 October 1914 reproduced below.
The following sketch of the k.u.k. Geniedirektion Brixen for the laying of the left wing of the Klausen-Villnöss barrier is dated as early as 21 October 1914. The sketch was obviously made and signed by Lieutenant Colonel Lempruch after his reconnaissance.
22 October 1914
Below is the recognosis report of the Obstlt. Lempruch of 22 October 1914 reproduced in full in the original. In red, Major General Friedl highlights the most important passages and adds short comments. As ‘1. Supplement’, the above plan of 21 October 1914 can be considered.
On November 17, 1914, the group leader in the General Staff Office provided the cover page of the Act of November 20, 1914 with the handwritten note: ‘As far as I can tell from the map, the position at Verdings also seems to me to be better than that at Pedratz (south of Feldthurns, A.d.V.). I therefore agree.’
Signature: Pf.
In the fascicle with the pres. No 5524 of the Military Command of Innsbruck of 1 November 1914, was additionally written in red on the envelope by hand ‘Urgent – as the equipment is to be carried out as soon as possible’. Furthermore, the relevant documents had been forwarded to the office of Chief of Staff Konrad von Hötzendorf, where they arrived on 31 October 1914.
On the inside of the fascicle was noted in black ink by hand:
Group command Bolzano
‘The eastern bank of the field fortification near Chiusa needs to be corrected, as the Villnöss valley will not be closed when it is situated at that time and the position in its left wing from the Tschanberg is always endangered. The accompanying recognosis report shall be reviewed. In the report in question, it must be stated whether the west bank part, too, would be best managed via Verdings-Latzfons. The matter is urgent as implementation is expected to take place as soon as possible.”
Unfortunately, only a large ‘R’ is recognisable as an annotation signature.
24 October 1914
Added laterally on the following document with Kurrentschrift:
"His Excellency (meaning G.d.K. Franz Rohr, commander of the army group of the same name and coordinator of the South-West defence, i.e. against Italy. N.d.V.) also got the impression on the spot that the east wing of the facility (Klausen-Villnöss, A.d.V.) had an accident. The Bolzano Group Command would have to be instructed to reconsider there, the result would have to be reported immediately.’ Signed: Pf
On 29 October 1914, the k.u.k. Military Command of Innsbruck received the reconnaissance report commissioned by the Bolzano Group Command of the Klausen Barrier with a focus on the Villnöß Valley, which was carried out by the Brixen Genius Directorate. This report was then annexed to the Faszikel ‘Sperre Klausen’ on 11 November 1914 and presented to General Rohr for review.
On 31 October 1914, in the work report of the Brixen Genius Directorate under ‘point 3) Klausen-Villnöß barrier’, the hope was expressed that once the decision of the Imperial Military Command of Innsbruck on the requested transfer of the left wing of the barrier to the Nafen – Teis line had been made, the construction work could be started immediately in an expected fair weather period.
4 November 1914
The k.u.k. military command Innsbruck reported on the status of the equipment work on 82. Equipment Day, that the continuous and very heavy rainfall, which has fallen in the last two weeks of October, has caused delays in work and major damage to the fortifications carried out in the ground. In the area of the Geniedirektion Brixen, 2. Line, one expects additional work in the field-based barrier Klausen – Villnöß, from Nafen to Theis.
Drawn Can-Horak, Field Marshal Lieutenant
7 November 1914
20 November 1914
On 20 November 1914, the final guidelines for the Klausen – Villnöß blockade for the construction of the new Nafen – Teis plant were issued. The cover page of the relevant file is reproduced below.
Following this act, the Bolzano Group Command issued the following order to the Brixen Genius Directorate:
On res. No 1673 of 22 October 1914 The opinion of the Bolzano Group Command on the above report will then be forwarded. The military command agrees with the requests made there and must use them as a basis for construction. Concerning point 4 above of the report of the Genius Directorate, it is noted that an officer of the Genius Directorate is to be appointed as site manager. and fortification res. Works manager assistant Josef Schmidt would be responsible for the detailed execution, according to the site manager. Attachments must be returned after copies have been made. The Res. No. 1085 of 4 November 1914 was accepted. The applications submitted will be notified at the same time to the G.D. Brixen as the basis for the amendment. Notwithstanding the above order, the k.u.k. Gruppenkommando Bolzano reports the following to the Military Command Innsbruck on 4 November 1914 in the case of ‘Block Klausen’, although the critical objections cannot be overlooked: The ban on Klausen is justifiably ambiguous. The group command at the time was right to move the left wing over the Villnösserbach (for tactical reasons) only there the left wing is little secured. The Eisack Bridge at the Villnöss stop is far and wide the only connection for both banks, and can only be secured by moving to the height of Gufidaun. The Tschanberg must now be given importance for the use of the external reserve. It secures an active defence on the one hand, and a connection with Val Gardena on the other. Since effective artillery support for active defense is preferably only possible from Verdings' point of view, the right wing must be advanced to this point. That Verdings' position with the flank guidance at Latzfons is undoubtedly tactical and fortificatory better than that at Feldthurns can be seen, and yet the latter cannot be dispensed with. By the way, the flight leaning by the procedure up to Verdings is rather better than before, and a not unfavorable attack terrain is denied to the opponent. It remains only to consider the danger of the monastery Säben, as a historical monument, but also in it I believe no deterioration of the situation takes place. If this consideration is correct, it follows that a system of fortifications is necessary for Klausen, which must take into account the tasks of the defensive and the possibilities of an offensive, and I make the following request:The facilities already built along the Zickerbach are to be left, as they remain of value for an offensive defense, and thus can serve as ____, with temporarily very weak crew. In the enclosed sketch, from an earlier file, the above request is indicated in pencil. Signature: Scholz
- Remaining of the previous installations with the exception of those along the Zickerbach in the left group, and installation of the advanced position at Verdings – St. Josef in the right group. (The last part is highlighted in red; A.d.V.) An intermediate group with a direct valley barrier west of the road bridge I consider necessary. However, their production could be postponed until an emergency occurs. Flank protections for both bibs and on the back via yarn, emplacements (positions) and travel paths for mobile artillery use in both Feldthurns and Verdings must be observed.
- The left group (underlined in red) would have to consist of: a.) the facilities around town and castle Gufidaun and the height west of it b.) the one requested by the Geniedirektion, north of the Villnösserbach
On the sketch mentioned by Scholz, his proposal, drawn with continuous blue lines, is clearly visible. However, only the left-hand part of the Klausen – Villnöß barrier, i.e. from the entrance to the Villnöß valley via Nafen to Teis, was realised. The forward positions on the right side of the barrier, via Moar zu Viersch – Verdings – Latzfons, were probably never erected because the front in 1. World War II, far from the Valle Isarco, in Trentino and in the Dolomites. He seems to be content with two mobile artillery positions in the right position wing, that at Verdings and the newly drawn artillery position between Pedratz and Feldthurns.
21 November 1914
On 21 November 1914, Lieutenant Colonel Lempruch confirmed in his letter to the military command in Innsbruck that the captain of the staff of genius Hugo Brandmayer had been appointed as the site manager for the additional facilities of the Klausen – Villnöß barrier and that he had been assigned as the executive body of the fortification assistant Josef Schmidt.
Furthermore, Obstlt promised. Lempruch that the construction work, if the weather permits, should begin in 1914.
According to the report on the state of the fortification works of the Brixen Genius Directorate, the Klausen-Villnöß barrier has meanwhile been completed on the right wing of the complex, which the fortification director had ordered during his inspection; existing single-row obstacles have been doubled everywhere.
28 November 1914
In the report on the state of the fortification works of the Genius Directorate of Bressanone, it was reported that the new left wing of the Klausen-Villnöß barrier was completely unplugged and the construction work would begin on Monday, November 30, noting that the observation stands would be carried out in concrete in the sense of the Przemysl experience.
4. December 1914
12. December 1914
In the last report of the Brixen Genius Directorate in 1914, concerning the Klausen – Villnöß barrier, it can be read that work on the left wing near Teis had progressed well, despite the difficulties caused by weather and terrain, and that the emphasis on the head protection could be started the following week.
2015
At the beginning of 1915, the work on defense in Tyrol had slowed down sharply for various reasons. On the one hand, there was a lack of skilled engineers, manpower (civil labor departments, prisoner-of-war labor departments) and explosives, on the other hand, the weather with snowfalls, snowdrifts and cold was to blame.
This prompted Kann-Horak, as the national defence commander, to send a letter of appeal to Franz Rohr, organizer of the defence against Italy, in order to remedy the situation. G.d.K. Franz Rohr replied by promising to organize remedy.
10 January 1915
In the equipment report of the Geniedirektion Brixen about the work in the 2. Linie, Teis – Villnöß, was entrusted with the overhead line by Captain Brandmayer. With him also worked 1 fortification officer, 1 Landsturm engineer, 1 fortification officer, 40 sappers, 60 volunteer workers, 2 carriers, 2 carts.
They all worked on the following projects:
- In the combat facilities at the construction of 3 bases with partly concreted, partly wooden head protection; The work was expected to be completed by the end of January.
- As additional work, the barracks had been built at the base immediately north of Teis. The obstacles in the width of 6 m were under construction.
- Behind the line they worked on the production of paths.
- The influx of obstacles was mostly carried out or partly ordered and thus on the way.
On January 27, 1915, the Imperial Military Command of Innsbruck sent a memorandum to the Imperial Ministry of War in Vienna and to General Franz Rohr, in which he asked for the assignment of politically unreliable workers' departments from other areas of Tyrol (they meant those from southern Trentino; A.d.V.) to the Genius Directorates of Bressanone, Trento and Riva.
There were fears that they could also bring in diseases. As a replacement, the Innsbruck military command asked for the allocation of 1,000 workers, who would certainly be dispensable from the outdated fortification work in Bosnia. In the end, an additional military-worker division of 280 men was requested for Bressanone.
29 January 1915
According to the equipment report of the Geniedirektion Brixen about the work in the 2. Line, Teis – Villnöß had Hptm. Brandmayer oversees the construction work. At his side were as senior personnel 1 Sappeuroffizier and 1 Landsturmpflichtiger engineer. As assigned workers, he was subordinate to 130 sappers and infantrymen as well as 120 volunteer workers with 10 carts.
As a status of the work, he reported:
- At the fighting facilities on the left wing were in the line Haubenberg-Teis-Gufidaun (first mention of the hood; A.d.V.) 5 bases with partly concreted and partly wooden headgear in work. The expected completion of the work was postponed until mid-February. For the most part, the supply of obstacle material was completed, and this information was valid for all installations.
- In the closed bases, additional work was carried out on caverns or shelters.
- Behind the bases of the fortification line, the route to the Haubenberg had been completed and in advance work was being carried out on the obstacle production.
9 February 1915
In the equipment report of the Geniedirektion Brixen is about the work in the lock of the 2. Line as follows:
The overhead line had Hptm. Brandmayer, as senior personnel, was assisted by 1 fortification officer and 1 engineer subject to Landsturm. As workers, 130 sappers and infantrymen, as well as 200 volunteer workers with 10 carts were in action.
On the state of play of the work:
- As far as the combat facilities were concerned, he reported 5 bases capable of defense for the left bank of the Isarco, namely:
1) Haubenberg Kote ¤ 1250; 2) faeces ¤ 1093; 3) Kote Δ 1027; 4) ⁇ south of Teis; 5) on the slope south † 814 the head protection is in work; 6) Work started at the base slope south-southwest † 814 m.
The obstacle manufacturing has an average width of 6 m. - Complementary work at the shelters in the bases: ad 1 ready; ad 2 commenced; ad 3 in progress.
Cavern at base: ad 3, 6m deep; ad 4, 5 m deep. - In advance, they worked on a tree and shrub clearing.
16 February 1915
The emergence of a controversy:
With pres. No. 3220, the k.u.k. military command Innsbruck became active again in the matter of missing, turned to General Franz Rohr and asked for the 1,000 requested workers from Bosnia, in addition, it was proposed to cover the missing 1,400 workers by Galician refugees. Since there was a great shortage of explosives, the reserves from abroad were proposed. There was also concern about qualified supervisors among the Sappeuren, as these were by no means sufficient. More and more often they were used as explosives detachments and this weakened their unity noticeably. It was also noted that the intention was to increase the Landsturm-Sappeur-Abteilung No. 1/14 in Bolzano (see later), which was currently only 50 men strong, by allocating surplus crew from the substitute companies p. 14 and p. 2. (These were then sent to Teis for training purposes; A.d.V.).
The Military Command Innsbruck received from General Rohr from Vienna an answer to the application in handwriting:
- The Bosnian-Herzegovinian employees will have to remain with the military command in Sarajevo for an indefinite period. The prospect was, however, that North Bohemian workers could be made available, but these would then have to be recruited as voluntary workers and would then be subject to the War Service Act.
- As far as explosive munitions were concerned, the Ministry of War promised to do everything possible to remedy the situation.
- Landsturm-Sappeur-Abteilung 1/14 would have to be used for special technical works, such as communications destruction or demolitions, a removal of Sappeure-Detachements for fortification works from this department does not appear to their advantage. Appropriate patrol leaders should be appointed as supervisory bodies for workers, military workers, etc., in the case of Capo's civilian formations.
Another note on the original document, handwritten on 19 February of the same year, contradicted the above instructions as follows:
The use of civilian supervisory bodies over the workers' departments in the fortification work had shown bad experiences, such as opposition of the civilian workers. One could therefore, unfortunately, for the time being not refrain from military supervisory bodies in order to maintain breeding and order and to promote rapid progress in work.
Signature: illegible
In the last handwritten note, Kann-Horak, commander of the Innsbruck military command, ended the controversy as follows:
With regard to the following and in the Pres. Circumstances described in No 3455/15 are agreed to the use of Landsturm Sappeure Division 1/14 personnel for the supervision of fortification and equipment works.
Date: 6 March 1915
Signature: Can-horak, Field Marshal Lieutenant
24 February 1915
In the equipment report of the Geniedirektion Brixen, the 2. Line noted:
Overhead contact line: Hptm. Brandmayer
Senior staff: 1 Fortification officer, 1 Landsturm-obligated engineer
Working class: 136 squadrons and infantrymen, 210 volunteer workers with 8 carriers and 7 carts
Status of work:
Completion work at the battlefields in the bases on the left wing. (Teiser side)
As far as the additional work is concerned, the Rohausbruch is finished in the caverns. All accommodation in the bases will be ready by the end of February. The creation of permanent obstacles around the bases and at intervals (between one and the other position; A.d.V.) is progressing.
1 March 1915
At the beginning of March, Hauptmann Brandmayer prepares an overview document on completed and still to be completed work on field fortifications 2. Line in the area of the k.u.k Geniedirektion Brixen.
On March 1, 1915, the following is recorded in the work report for the Klausen-Villnöß combat facility:
Position Feldthurns-Gufidaun:
Recognosed, projected: Fireworks assistant Schmidt
Overhead contact line: Lieutenant Colonel Lempruch
Construction management: Fireworker fortress assistant Schmidt
Positions Theis – Haubenberg:
Recognosed, projected and overhead line: Hptm. Brandmayer
Construction management:
- 26 November 1914 to 30 January 1915
Fireworker fortress assistant Schmidt - from 30 January 1915
Lieutenant-Colonel of Ettmayer.
Start of work: 26 August 1914
End of work: 8 September 1915
in fleeting (i.e. unsystematic) style
Beginning of further work that has not yet been completed: 26 November 1914
9 March 1915
In the equipment report of the Geniedirektion Brixen about the work in the barriers of the 2. The Klausen-Villnöß line was written as follows:
Overhead contact line: Hptm. Brandmayer
Senior staff: 1 Fortification officer 1 Landsturm-obligated engineer
Working class: 136 squadrons and infantrymen, 240 volunteer workers with 22 carriers and 7 carts
Status of work:
In the Klausen-Villnöß battle complex, the bases on the left wing are in completion. Emphasize the head protection. Creating spacious obstacles around the bases and at intervals. Some additional work on the shelters in the bases, which are usually already usable. In the caverns work out the normal profile, masonry.
11 March 1915
In the Pres. No. 5116, Equipment works - Completion, the Military Command Innsbruck tried the Coordinator of Defense against Italy (future South-West Front; A.d.V), General of the cavalry Franz Rohr, to describe the delay in the erection of the field positions in Tyrol and to enumerate all difficulties. It also admitted misperceptions:
The working hours determined in the General Equipment Drafts were based on the premise that many volunteer workers would be available initially and the military workers' departments would be available eleven days later. In fact, the number of volunteers ranged from half to a third of what was expected, while the military workers' departments had to be immediately called into service due to a lack of troops.
The minimal construction works against “attacks” (originally “procedure”; A.d.V.) lasted almost twice to three times the time instead of 14 days, they were generally finished by the end of November, which was also reported by the end of September 1914.
However, it was already clear to the Innsbruck military command in September that the reached stage could not be considered as the completion of the fortification work. Thus, the Genius Directorates were instructed: to complete ‘further design of the intervals, widening of the obstacles and cavern structures’ and thereby bring it to the highest possible level, which was possible without significant damage to crops and buildings. The fortification work of the 2nd party had to be carried out. Line without disturbing the work on the 1. line is made. They were partly terminated in the month of October 1914, partly interrupted due to snowfall. Furthermore, the ordered exploitation of the experiences of Przemysl, Cattaro and Bileca was integrated. In addition, unexpected new installations such as those at Creino and Biaena (Valle di Gresta, TN; A.d.V.), so that all construction activities entered a new stage. Therefore, a new termination date had to be determined. The Military Command of Innsbruck fixed him for the most urgent works at the end of January 1915 and for all other works at the end of February 1915.
But now nature came forward with weather disasters such as downpours, storms and unusually heavy snowfalls, which overturned every schedule. Therefore, it had to be reported on 3 January that the target termination date of the end of February could not be met.
During this time there was also a lack of everything, of genius officers, workers, means of transport for the transport of the obstacle components, etc. As a result of these obstacles and the certainty that the country would receive no influx of troops in an alarm case, the work on many field fortifications located in the south of Tyrol, such as Serravalle or Pasubio, was greatly reduced or even stopped.
Finally, when, with the first days of March, the shortage of workers seemed to have been remedied, the supply of materials was again possible and a weather improvement was to be expected, the completion of the work was set for the end of March. At the end of the report, it was reported: ‘... that, to the extent that conditions will allow, improvements to positions will continue beyond the above-mentioned dates’.
Thus, at the end of the report, the Innsbruck Military Command continued to signal a postponement of the date as possible.
Date 11 March 1915
Signature: Can-horak, Field Marshal Lieutenant
Genaral Rohr confirmed receipt of the report on 1 April 1915 with his signature on the original document.
24 March 1915
Equipment report of the Geniedirektion Brixen about the works in the barriers of the 2. Line, Teis-Villnöß, Verdings:
Overhead contact line: Hptm. Brandmayer
Senior staff: 1 Sappeure-Fortifikationsoffizier, 1 Landsturmpflichtiger engineer
Working class: 90 squadrons and infantrymen, 230 volunteer workers with 22 carriers and 6 carts
Status of work:
In the combat facilities, the concreting of the combat positions in the bases on the left wing (Teiser side) continues, more than half of the facilities are already capable of defense and the obstacles are usually ready.
As far as the additional works were concerned, the caverns in the Rohausbau were finished, the shelters partly finished, partly in completion.
9 April 1915
In the working report on the state of the genius equipment in the area of the genius directorate Brixen, Captain Brandmayer named six main bases for the left wing of the position Klausen – Villnöß (Teiser side) together with their equipment (today's construction progress; A.d.V.).
24 April 1915
In the working report, Hauptmann Brandmayer states the following under Theis – Verdings:
6 May 1915
The fact that the Geniedirektion Brixen was still missing obstacle material at that time can be seen from a letter from the War Ministry announcing a delivery of 45 wagons with obstacle bars made of 20 mm round bars. As we shall see, part of this delivery may then have reached Teis.
Captain Brandmayer confirmed the letter on 12 May 1915.
On May 23, 1915, Italy declared war on Austria-Hungary.
Other men left their villages and towns and went to the south-west front for defense, but wherever possible they built on the defenses of the 2. Continuation of the line, often with a reduced team. It was not yet clear whether the Italians would break through the thin-sown defense of the Tyroleans or not. Only with the arrival of the German Alpine Corps was the front against Italy more secure and somewhat stabilized.
29 May 1915
The fact that even in the Teis-Verdings barrier, as the Klausen – Villnöß barrier was increasingly referred to, not everything necessary for the expansion of the field fortifications had arrived or some was only delivered in the course of the spring, proves the invoice issued by Anna Reiserer, crown hostess in Klausen, on 29 May 1915 for the transport of obstacle material to the positions at Teis.
Invoice from Anna Reiserer, crown hostess in Klausen, for a transport of obstacle bars and the corresponding receipt.
Also interesting are the local stamps used on the documents:
that of the Geniedirektion Brixen and the far rarer of the
k.u.k. Military Works Management Teis
One of the few photos we know about the Teis – Verdings blockade: It shows four officers sitting in front of a newly erected wire obstacle. The two on the right are national shooters, in the 2. Officer from the left could be the site manager Oblt. Ettmayr is acting. Remarkable is the design of the obstacle, which was built from normal wire and barbed wire.
21 June 1915
In the equipment report of the Geniedirektion Brixen about the work in the barriers of the 2. Line, Teis-Verdings, is clearly written:
Teis: Completion work is underway on the left wing.
Verdings-Feldthurns: on the right wing, the work is temporarily suspended, but will return to flow, albeit at a slower pace, according to the release of the labour force on the left wing. The workers were diverted to Landro.
In all other installations of the 2. The work progresses satisfactorily along the line.
In the last three known equipment reports of the Geniedirektion Brixen of 23, 25 and 27 June 1915, one can see a certain disappointment Hptm. Brandmayers on ‘so much useless work’.
23 June 1915
Teis – Chiusa, from where a workers’ section had to be sent to Landro. However, work on the right wing of this installation – Verdings position – has also been ongoing for two days. Otherwise, no important changes, the work is progressing uniformly everywhere.
27 June 1915
I (Hptm. Brandmayer A.d.V.) had to according to Stern with the determination to form carrier columns. 5 workers' departments with a total of 1020 men. The Teis barrier, left wing capable of defense. Old right wing as well (meaning the positions from the right bank of the Isarco over Feldthurns to Garn.; A.d.V.). New right wing only in the beginning of construction (here he probably meant the never completely rejected plans from Feldthurns to Verdings; A.d.V.).
25 June 1915
Equipment report of the Geniedirektion Brixen about the works in the barriers of the 2. Line, Teis-Villnöß, Verdings,
Last entry found:
This is where work rests, as the workforce has been withdrawn and this in general.
However, the defense capability is consistently achieved!
Work is still being carried out only with the approval of his Excellency, the commander of the German Alpine Corps!
(G.d.A. Konrad Krafft von Dellmensingen; A.d.V.)
One of the last comments on the Yarn – Teis positions can be found on 1 August 1915 on a map summarising the state of defence buildings in Tyrol.
Detail from the above overview map with the positions between Teis and yarn. On it is the left wing, Gufidaun – Teis, with red Colour as finished and the right wing, between yarn – Verdings – Leitach, in blue drawn, still in project planning. The rear, already realized bases between Feldthurns and the gorge no longer appear at all.
Summary review
To avoid misunderstandings, it should be noted that in the documents the field positions from Klausen to Teis appear at different times with different names adapted to the respective places of work:
- Chiusa blockade - Gufidaun
- Chiusa block - Villnöss
- Teis – Feldthurns barrier
- Chiusa blockade – Teis
- Block Teis – Verdings, to name but a few.
On the question of how many people have now finally worked on the Klausen – Teis blockade, I offer the following overview:
First overview board
Second overview board:
for the month of June, from 6 to 24 June 1915, the working class in the Teis – Verdings barrier could be precisely determined.
According to my research to date, there were no Landsturm workers or prisoners of war in the Klausen – Teis block that had built on the defences; But certainly members of the Genius Directorate of Bressanone, voluntary workers (e.g. Klausner intelligentsia), workers who were subject to the War Service Act, sappers and imperial hunter, state shooter and stand shooter trains sent for training.
In conclusion, it can be said that the k.u.k. army command and the Tyrolean national defense planned for almost 90 years (1833 to 1916) at a dam near Klausen and finally also built in the field. However, as a result of different views in the Planning Commission, because of the fortification priorities in the wide plains of Galicia as well as in the not quite pacified Bosnia-Herzegovina and not least because of a lack of money, the facilities were never completely realized.
From today's point of view, one can speak of luck that such a plan could ultimately never be realized in the Brixen area. Anyone who knows what urban development difficulties and economic restrictions Trento had to contend with as a fortress city in the k.u.k. period must be grateful that Bressanone with its immediate vicinity was largely spared from such military projects.